Check Your Package Free →Florida law requires a recorded Notice of Commencement when the contract price is greater than $5,000 ($15,000 for repair or replacement of an existing heating or air conditioning system). Timing can vary, so confirm with the Miramar building department whether it is due at application or before the first inspection.
Only LICENSED MECHANICAL CONTRACTORS can apply for AC permits — NO owner-builder for HVAC. NOC threshold for AC is $15,000 — much higher than the standard $5,000. If roof-mounted or gable-wall-mounted unit: TWO (2) sets tie-down engineered details s/s by PE PLUS a separate Building/Structural application required.