  1. Before you start: registration and insurance
  2. The application package
  3. Product approvals and engineering
  4. Affidavits and certificates
  5. Inspections, in order
  6. Fort Lauderdale specifics to plan for

Fort Lauderdale takes roofing permits through LauderBuild, and only digitally. Paper applications are no longer accepted, and paper applications submitted earlier cannot be digitized. This guide walks through the package in the order you will need it. For the complete line by line list, use the Fort Lauderdale roofing checklist.

Before you start: registration and insurance

The application package

Product approvals and engineering

Fort Lauderdale requires a Miami-Dade County Notice of Acceptance (NOA) for all roofing products, along with the complete roofing package under Florida Building Code Chapter 15. For the background on why, see our HVHZ explainer.

Circle the relevant information on each NOA. Do not use a highlighter: highlighted NOAs are rejected. Include all sheets of every NOA.

Affidavits and certificates

Inspections, in order

The checklist lists the roofing inspection sequence as:

  1. Tin-cap and renailing
  2. Mop-in progress
  3. Tile or shingle in progress
  4. Final structural

Fort Lauderdale specifics to plan for

FAQ

Does Fort Lauderdale accept paper roofing applications?

No. Applications are 100% digital through LauderBuild.

Can I highlight my NOA?

No. Circle the relevant information instead. Highlighted NOAs are rejected.

When is the Hurricane Mitigation Affidavit due?

At or before the final inspection. It applies to re-roofs on homes assessed at $300,000 or more under Florida Statute 553.844.

Sources

Check your package before you submit.

Upload your documents and see what is missing against your city's checklist.

Start Free Analysis →

3 free analyses to start. No credit card needed.

General information, not legal advice. Requirements change, so confirm current rules with your building department.